PROJECT OVERVIEW

The entire project was originally conceived as one large project with different components combined together but in order to accelerate the overall construction schedule, the project has been divided into five construction packages :-


Package I : Construction of flyover over Love Grove junction at Worli
Project Status : Commissioned

Package II : Construction of cloverleaf interchange at Mahim intersection
Project Status : Commissioned

Package III : Construction of solid approach road from the Mahim intersection up to the start of the Toll Plaza on the Bandra side and a public promenade
Project Status : Commissioned

Package IV : Construction of Cable Stayed Bridges together with viaduct approaches extending from Worli up to the Toll Plaza, intelligent Bridge System (IBS).
Project Status : In-Progress, estimated to be commissioned by 2009

Package V : Improvement to KAGK Road 
Project Status : Not started
PROJECT DETAILS

BANDRA WORLI SEA LINK PROJECT

connecting island and suburbs of mumbai